Hello,

Thanks for all your answers. I create a multiple counter plan, but i have a new problem.

My cycle sets are:

 

first cycle set: 1 month or 250 hours (ex: with task list with 3 operations)

second cycle set: 6 months or 1000 hours. (ex: with task list with the 3 operations of the first and 2 more operations)

 

E did the first cycle set with 3 Repeat Factor and the second cycle set without repeat factor, but what happens if the machine after 750hours, don´t work 250 hours before 1 month? The cycle goes to the second cycle set and then it can´t do the maintenance after 1 month, but only after work the 1000 hours or after get the 6 months. Right?

What i can do to solve this? It is not posible to do only one maintenance plan?

 

Thanks a lot,

Tiago